The Radius at Sixth Avenue and First Street is being replaced and is ready to be poured this week.

• Nearly all of Seventh Avenue between First Street and Broadway has been excavated and a base put down. Just a little bit on the west side remains.
• The original plans had called for asphalt to come to town tomorrow, but that has been delayed to next Monday. Part of the delay is the fact that the gravel has not been coming in fast enough.
• With the delay, that will actually allow AP & Sons, Inc., to get more done which will allow the pavers to lay down more asphalt before catching up to AP & Sons, Inc. crew
.

Wright & Sudlow crew poured the roll-over curve on the south side of the high school on Fourth Avenue. The rest of the sidewalk and radius will be poured this week. Once completed, AP & Sons, Inc., will excavate Fourth Avenue from Broadway to Main Street.